PM Surya Ghar- Muft Bijili Yojana RDSS- Revamped Distribution Sector Scheme MSPDCL Tariff Order for FY 2025-26 Internal Complaints Committee (ICC)-MSPDCL Suo Moto Disclosure under Sec. 491)(b) of the Right to Information Act, 2005 PM Surya Ghar- Muft Bijili Yojana RDSS- Revamped Distribution Sector Scheme MSPDCL Tariff Order for FY 2025-26 Internal Complaints Committee (ICC)-MSPDCL Suo Moto Disclosure under Sec. 491)(b) of the Right to Information Act, 2005
construction

PROJECT UNDER SASCI

event Started: 26 Nov 2025
flag Target: 30 Nov 2026

PROJECT UNDER SASCI

Project 1: Supply, installation and commissioning of medium voltage covered conductors (MVCC) replacing the existing bare conductor in areas covered by IED-I and IED-II MSPDCL division 11 kV covered conductor project involves replacing bare overhead conductors with insulated conductors for enhanced safety, reliability, and reduced environmental impact in power distribution systems.

These covered conductors, also known as Medium Voltage Covered Conductors (MVCC), offer improved protection against accidental contact, vegetation interference, and corrosion, while potentially reducing maintenance needs and enabling more flexible routing.

  • Approved Project Cost: Rs. 59.08 crore

  • Districts to be covered – Imphal West

  • 11KV Circuit Length to be replaced with covered conductor – 205.60 km.

  • LOA Awarded on 26th November 2025

  • Target Completion: November, 2026

  • Current Status: Material Supply completed and 20 % of the erection works has been completed.

Project 2: Supply & laying of 11 kV XLPE Al. Cable (1.79 x 2 km -double run) for underground cabling (3x300) sq.mm for providing alternate 11 kV supply to Khuman lampak main stadium from 33/11 kV Khuman sub-station.

The project aims to:

  • Provide an alternate 11 kV underground power supply from the 33/11 kV Khuman Sub-station.

  • Ensure uninterrupted and stable power during events and peak load times.

  • Improve voltage regulation, load balancing, and system reliability.

  • Enhance the stadium’s operational readiness, especially during national and international sports events.

  • Approved Project Cost: Rs. 2.87 crore

  • Areas covered: Khuman Lampak Stadium

  • 11 kV XLPE Al. Cable for Underground Cabling (3x300) sq.mm – 1.79 ckt. km. (Double circuit)

  • LOA Awarded on 16/12/2025

  • Target Completion: March, 2026

  • Current Status: Material Supply completed and 40% of the erection works has been completed.